Introduction to Project Management for IAM Projects (v2)

By Graham Williamson, Corey Scholefield

© 2021 Corey Scholefield, Graham Williamson, IDPro

To comment on this article, please visit our GitHub repository and submit an issue.

Importance of Project Management

IAM practitioners may be familiar with the scenario of an IAM project proceeding under the control of an IT systems group without a formal project manager. While this method of deploying a new product or service may be considered an expedient way to get a system installed or updated, it is likely to cost the organization more money in the long term. An IAM service is connected to many critical systems within an organization. To make changes to that service without considering the possible impact on the various connected systems, without managing the required resources, or without keeping all stakeholders advised of the effort, will result in a substandard deployment.

Project management does have a cost: it is typically between 5-10% of a project's total expenditure, but it represents the best return compared to any other investment an organization is likely to be afforded.

Terminology

Readers interested in pursuing information on project management should review the Project Management Institute (PMI) Framework and the PMI Body of Knowledge for further information.[2]

Characteristics of a Project Manager

In the IT sector, a project manager is often seen as having little authority over staff or project stakeholders. They are expected to bring a project in on time and within budget with minimal assistance from upper management and minimal visibility within the organization. In reality, a project manager needs sufficient authority and resources to monitor and manage their project adequately. They also need regular communications with a steering committee consisting of representatives from upper management.

Two prime characteristics are essential to a project manager:

Predictability Management doesn't like surprises. Therefore, a project manager should determine and report on a project's duration and related costs to a defined degree of confidence.
Flexibility Gone are the days when a project manager slavishly followed an approved Gantt chart to the detriment of anyone who wants a change. These days, IT projects will typically undergo several baseline changes during execution to accommodate scope changes, dependencies on other projects, and changes in resource availability.

Project managers require competence in the five components of project management:

PMI Framework

By definition, a project must have a start and a finish. “Business as usual” is never project work and does not require the skills of a project manager. Before the beginning of a project, there will be some preparatory work to define the concept. Between the commencement and completion, there are discrete stages that define the project work. It is not until after project completion that the deliverable will enter an operational status and become business as usual.

Diagram showing the basic project lifecycle, from Concept to Planning to Execution to Operations.

Figure 1 - The Project Lifecycle

Concept

Projects come out of a need. In the IAM world, examples of such a need include reducing costs and improving security by using identity information more effectively for onboarding and offboarding staff or a need for an enterprise LDAP directory upgrade. Such projects are typically initiated by an IT resource rather than a business resource, though a line-of-business resource might also initiate a project (e.g., to move an application from an on-premises environment to the cloud to save capital expenditure budget). The project sponsor will communicate the requirement, set the project charter, and evaluate the required activity's cost and duration. The sponsor will typically fund this stage and then engage a project manager to complete the planning stage.

Planning Stage

Once approval to proceed has been received, the project manager will engage with the stakeholders to define the project scope. It is common for the size and complexity of the project to increase at this point. A project where the initial scope is to deploy identity management software to establish AD records and email accounts might see a feature request for including provisioning into corporate applications. Alternatively, a stakeholder may try to introduce a request for additional functionality such as periodic attestation reporting and re-certification. The project manager must ensure that the appropriate project stakeholders are engaged to define the full scope of the project.

The project manager will engage subject matter experts to quantify the work required and construct the project schedule. The Planning Stage will develop a Project Plan that will include:

Schedule A schedule is typically expressed via a Gantt chart in classic project management. A high-level Gantt chart is also recommended for Agile project management. The schedule will define the timeframe and resources required for the project to calculate the cost.
Stakeholder Analysis The project manager will construct a list of project stakeholders. This list should include the sponsor, finance manager, human resources (HR) manager, system owners, and representatives from the IT groups that will be engaged in the project.
Resource Plan A basic tenet of project management is that the desired resources are never available; they are typically fully engaged in other activities. The project manager must negotiate with the appropriate stakeholders to get the desired resources assignment and alter the project schedule accordingly.
Communications Plan The project communications plan defines the "who" and the "how" for a project manager to report on project progress. The project team will likely have a file folder, wiki, or SharePoint site for the project. The project manager will regularly email a project report to the Stakeholders and send meeting agendas and status summaries to the steering committee before the project review meetings. The Project Plan should include a Communications Register that logs all communications with the stakeholders and within the project team.
Quality Management A mechanism to ensure adequate quality in project deliverables should be defined. This mechanism should include management reviews of project documentation and properly constructed test and release procedures.
Risk Management A project manager constructs a risk register that identifies the anticipated risks, quantifies them in terms of probability and impact, and includes appropriate risk mitigation activities.

At the end of the Planning Stage, there should be a good understanding of the project activities, timeframe, and cost. Typically, the project cost and duration will be known within a 10% margin.

In terms of time and money, this understanding of project costs allows the organization to make an informed decision as to whether they want to dedicate the necessary resources to a project. A decision not to proceed with a project is just as much a successful outcome for a project manager as a decision to proceed. It means that the organization has been spared the expenditure of resources on a project that they might otherwise have prematurely terminated, resulting in associated sunk costs.

Deployment Stage

The project deployment will vary depending upon the project management mechanism to be used.

Classic

In classic project management, the project manager will manage all project activities according to a detailed schedule that shows all the individual tasks, assigned resources, and duration. The project team will regularly hold meetings to review progress and discuss any issues that the project manager may need to escalate to the steering committee.

The components of a classically managed project are:

Team meetings The project team should hold regular progress-review meetings (weekly or bi-weekly). These meetings allow everyone to mark progress against the Gantt chart and determine what issues, if any, must be escalated to the steering committee.
Steering committee The project manager will periodically present to the steering committee to review progress to the project schedule and act on any issues that the team has identified. The project status report should include the progress made since the last meeting, any issues to be resolved by the steering committee, and the planned activities for the next period.
Phase transitions The project schedule (Gantt chart) will show the phases that comprise the project. At the end of each phase, the steering committee will review the deliverables for that phase and determine whether a phase transition can be approved.
Deliverable acceptance Each project deliverable should be formally accepted. This acceptance will typically involve the appropriate stakeholder(s) who must agree that the deliverable has been produced to an adequate quality level.
Project closure A project should always include a proper project closure procedure. This procedure will typically involve a formal project review that will document the activities that went well and any learnings from the project. "Those who don't learn from history are doomed to repeat it."

Agile

Many organizations have now adopted Agile project management for the execution phase of their projects. Agile-run projects make it easier for changes to be made in the way a project proceeds and avoids delays that can occur in "classically" managed projects when issue resolution is held up awaiting a steering committee meeting. Agile projects divide a project up into short tasks reviewed every few days in "stand-up" meetings.

Project wall The essence of Agile project management is visibility. The Project Wall provides a physical or virtual place where the project team can view the completed, current, and waiting tasks and resource assignments.
Sprints & Scrum These terms are used differently depending upon the context. Scrum is a framework that uses an iterative process to deliver a defined piece of functionality. It could be a product, service, or a new piece of functionality for an existing product (e.g., deploy a DBMS connector to the IAM environment). A sprint usually describes a scrum component, a time-limited activity that contributes to a scrum deliverable (e.g., 30 days for the development of the reporting module).
Deliverable acceptance One area that can suffer when using an Agile project management approach is reviewing and accepting deliverables. A sprint team sometimes advises on completing a piece of work and moves to the next without formal acceptance of the deliverable. A mechanism to record acceptance of a module or deliverable is needed. Acceptance testing will verify that the requirements established for a viable product have been achieved and are demonstrable.
Project closure In a classically managed project, a team meeting can be dedicated to the requisite project review. In an Agile project, in which many participants have contributed to the outcome, it is sometimes difficult to manage the project closure. A mechanism is required for all participants to agree that a project has been completed and ensure the resources used can be reassigned.

PMO Issues

In organizations with a Project Management Office (PMO), an IAM project must follow the corporate procedures. Typically, a PMO will have defined gating factors, or ‘gates,’ through which all projects must pass. For instance, there will normally be a project approval gate in which the appropriate managers will review the project plan and indicate their approval. There will usually be a gate in the form of a budget review to approve the assignment of resources. Similarly, there might be a gate in the form of an architecture review to approve the solution architecture. Finally, there should be a review of the governance outcomes as a necessary gate to the project. The PMO should orchestrate all these activities.

One of the benefits of a PMO is the visibility it gives to projects within an organization. This visibility is beneficial to the IAM team; it allows them to ensure any projects with an identity component are properly identified and accommodated in the appropriate work program. For instance, if an authentication gateway is being installed, any application undergoing development should be modified to use the gateway rather than maintaining LDAP lookups. Without a PMO, it is sometimes difficult for the IAM team to impact projects.

A PMO provides the opportunity to educate project managers on identity issues and to insert IAM requirements into IT projects within an organization. A project manager will use the PMO framework to:

  1. manage the project through the project gates;

  2. communicate the project's progress to the organization's management;

  3. gain acceptance within the organization that the project goals were completed within the approved budget and schedule.

IAM Projects

It’s often said that a good project manager can keep a project on track regardless of the topic. While this may be true, if a project manager for an IAM project is not competent in the subject, they will be disadvantaged. It is recommended that they engage a project lead who is familiar with the components of an IAM environment and understands the skills-base within the organization.

Example Project

Let’s assume the project is to replace the existing IAM processes used to onboard a new staff member or contractor with a new system purchased from an IAM solution vendor. The sections below work through the different project stages for such a project.

Planning

The single most important element to define for an IAM project is the project scope. The IAM environment touches so many operational components and processes within an organization; the PMs role means they must clearly communicate to all stakeholders the full scope of the project. To properly determine the scope of an IAM project requires a PM an understand the nature of the IAM solution and its impact on other systems in the organization. The Addendum suggests some questions that should be asked in the planning phase of an IAM project.

The PM is responsible for making certain the scope of the project is clear. Too many IAM projects proceed with misunderstandings regarding the project scope. The IAM project lead, for example, might think the project is to implement a provisioning module, whereas the application owner might think the goal is to provide better authentication functionality. The auditor, in turn, might want improved governance. Reaching a common agreement on the scope will focus all stakeholders on the extent of the project.

The following items are often inside the scope of a project of this nature: configuring and deploying the IAM tool, integrating with the email system, integrating with the system(s) that provide enterprise resource planning (ERP) functions (i.e., the computer systems that support the organization's operations). The HR system and the financial management system, however, are out of scope for this example project. While tight integration with HR could improve both systems—the HR system potentially able to increase its span-of-control and the IAM system benefitting from tight integration with HR for better provisioning of staff entitlements (e.g., training status, project membership, and employment status of staff)—the HR department is often reticent to make any changes to their onboarding and offboarding procedures.

The Finance department also has challenges that discourage them from agreeing to anything that will impact their systems. They typically maintain a fine-grained authentication capability within the financial management system and often distrust any external entity’s capability to do this. Externalizing access control to the IAM system will typically be less expensive and improve security but working with Finance will require its own focused effort.

In scope will be the applications that will rely on the IAM system. The PM must communicate with the system owners of each of these systems and determine what data attributes are required for users accessing each system. For example, the email system will need to know a user’s first and last names and, likely, middle initial, to construct their digital identifier correctly. It might also need to know their department or group memberships. Ideally, email systems should participate in a company’s single-sign-on (SSO) solution (i.e., users will be authenticated as part of the SSO solution used in the organization).

The computer applications that provide operational functionality to users should also use the organization’s SSO solution. In the real world, such applications might include a production machine, a process control system, an asset control system, a learning management system, a health monitoring facility, a vehicle registration, and so on. Any computer system that must be protected via an access control mechanism that ensures appropriate users only get access to the facilities to which they are entitled should be tied into the organization’s SSO solution. The project manager must ensure the requirements for these applications are canvassed at the commencement of an IAM project.

Organizing

The success of an IAM project depends upon how well it is organized. This dependency relates to how well the PM utilizes the hierarchy within the organization. All too often, the execution of an IAM project is left to the people in the IAM unit within the company. This is poor practice because the IAM unit has an operational role in maintaining the IAM environment; an IAM project, however, is a time-limited initiative that will stretch the ability of the IAM unit and divert resources from their task of managing the IAM environment. While personnel with IAM experience should be involved in the deployment project, if they are seconded from the IAM unit, they should be backfilled with other personnel while they are engaged on the IAM project.

The following activities are recommended for the successful ‘organizing’ of an IAM project:

Resourcing

It’s a project management maxim that the preferred resources are never available. Good staff are very busy and cannot be easily seconded to a project. In an IAM project, it is essential that personnel with detailed knowledge of the company’s identity management systems and policies be involved. The PM must be able to negotiate the availability of critical personnel and modify the project schedule accordingly.

As noted above, the project’s budget must accommodate backfilling personnel seconded to the project. If it is necessary to ’buy-in’ resources, the steering committee will typically decide on the final resourcing plan and may choose to use contractors for the maintenance activity and assign experienced IAM staff to the IAM deployment project.

A perennial problem for an IAM project is how to build IAM staff competence in a new IAM tool being acquired. The options include:

It is unrealistic to expect, even experienced, IAM staff to develop competence in the new package without hands-on experience.

This is the most realistic option because it puts some onus on the vendor to ‘make it work’ and ensure technology transfer to the IAM staff.

This is not ideal since, without the active involvement of the IAM team, the likelihood of successful integration of the IAM solution into the organization’s operations will be difficult.

Since the PM of an IAM project typically has no functional authority within the organization, they must use the steering committee to get the right resources assigned to the project at the right time.

Directing

The Directing element of an IAM project will vary greatly depending on whether a classical or an Agile project management methodology is being followed.

Classic

The Gannt chart becomes the main tool for directing the project. The PM will ensure tasks are commenced on time and progress to plan. This will be achieved via a review of the schedule in periodic team meetings, typically held on a weekly basis. Team members will report on the progress to plan for each task to which they are assigned. For tasks behind schedule or expecting to encounter problems, the PM will attempt to put a contingency in place. If a slip occurs, the PM must go back to the steering committee with a recommended strategy and seek approval or additional direction (for example, direction to accept the slip and modify the Gantt chart or direction to invest the resources necessary to restore the original schedule).

Agile

The PM will establish regular ‘stand-up’ meetings, typically several times a week, at which each ‘sprint’ is reviewed and moved on the Project Wall from ‘waiting’ to ‘current’ to ‘completed.’ Each scheduled task will be discussed and any impediments to completing a ‘sprint’ will be noted by the PM and addressed with appropriate management. For instance, transition to production might have to occur during non-business hours, and coordination with HR may be required to ensure the IAM data file is current.

The PM will raise unresolved issues at the next steering committee.

Controlling

Probably the PM function that is most often performed badly in IAM projects is control.

Control is a function of project management that provides feedback to the PM regarding the likelihood that the project will meet its schedule and budget constraints. PMs will typically think that if they have planned well, have organized the communication and quality assurance, have adequately resourced their project, and are directing the project tasks, nothing else is required. But the stories are legion that IAM projects have overrun because they impact so many functions within an organization. Managing this impact is where control comes in. Given that you cannot manage something if you cannot measure it, monitoring progress to plan is at the core of the control function. A tried-and-true tool in the PMs toolkit is Earned Value Analysis (EVA). EVA involves calculating the budgeted cost of work scheduled, the budgeted cost of work performed, and the actual cost of work performed. These calculations will compare the percent completion against budget spent and quickly identify a project that is experiencing overspend or over-budget issues.

Another tool to use to calculate the project’s performance indices is the use of quick ratios to gauge the probability of an on-time and in-budget project completion.

A third useful tool is the S curve that tracks the resource burn rate to ensure the project expenditure reduces appropriately, particularly at the end of a project. This careful management of the resource burn rate is important for IAM projects since there are always additional tasks, such as system documentation, that are often not properly accommodated in the project schedule at project inception. These should not be added to the scope of the project. Instead, they should preferably be completed as part of standard operations (i.e., outside the project).

Conclusion

Project management methodology should be applied to all IAM projects, even small ones. Project management ensures that a structured process is applied to the activity and that the impact of the activity on affected business units will be considered and, if necessary, included in the planning. Failure to manage an IAM activity as a project will raise the likelihood of mistakes being made and additional costs being incurred.[3]

Author Bios

Graham Williamson

Graham Williamson is an IAM consultant working with commercial and government organizations for over 20 years with expertise in identity management and access control, enterprise architecture and services-oriented architecture, electronic commerce and public key infrastructure, as well as ICT strategy development and project management. Graham has undertaken major projects for commercial organizations such as Cathay Pacific in Hong Kong and Sensis in Melbourne, academic institutions in Australia such as Monash University and Griffith University, and government agencies such as Queensland Government CIO’s office and the Northern Territory Government in Australia and the Ministry of Home Affairs in Singapore.

Corey Scholefield

Corey is currently a Sr. Technical Product Manager with Workday, supporting operations engineering service delivery for Workday's cloud-ERP suite. Corey has a background in public-sector identity-management, having spent over 15 years working in higher-education, with positions at both University of Victoria and BCNET in British Columbia, Canada.

At BCNET, Corey led a federated-identity service bureau which supported regional adoption of eduroam and SAML capabilities under the umbrella of the Canadian Access Federation. At the University of Victoria, Corey's team established an identity-management program that supported campus-wide access-management needs. Corey has deployed many IDAM technologies including OpenLDAP, CAS SSO, Sun IDM, Shibboleth IDP, and SailPoint IdentityIQ.

Change Log

Date Change
2021-06-21 Editorial updates; substantive revisions to IAM Projects section

Addendum: Questions for an IAM Project Manager to ask

Identity Management

Access Control

Governance

[1] Scrum Alliance, “Your Quick Guide to All Things Scrum,” accessed 29 June 2021, https://www.scrumalliance.org/about-scrum/overview.

[2] Project Management Institute website, https://www.pmi.org/, accessed 29 June 2021.

[3] Project Management Institute, "PMBOK® Guide and Standards - Practice Standards & Framework," accessed 29 June 2021, https://www.pmi.org/pmbok-guide-standards/framework.